Rappa Resources 2018
High frequency technology.
Complete stainless steel constitution.
Plant: Gold Recovery
Quanity: 1 off Wet ESP
Guarantee Offered: 50mg
Lafarge Manresa ESP & Downcomer Project 2012
Scope was demolition of 2 ESP’s and installation of 2 new units. This was a full turn key project.
Project duration of 100 days including site establishments. Emission guaranties of below 50mg was achieved.
Unilever Maydon Wharf Durban 2015
ESP was pre assembled in a staging area. Support structure was erected in position.
ESP was installed in 3 sections and ESP completed in record time of 14 days.
Client: Unilever
Plant: Biomass Boiler
Capacity: 20 t/hr
Quanity: 1 off
APC Equip: Erection of 1 off BETH/ J&C ESP.
Erection Period: 1 Month
Guarantee Offered: 50mg
Guarantee achieved: < 50mg
ZPC Hwange Project 2013
Pre-assembly of ESP internal components. Alignment and storage jigs. Site establishment & pre shut preparartion.
Complete replacement of all Electrical works.
TFD York Timbers Sabie – 2014/2015
Client: TFD
End User: York Timbers
Plant: Biomass Boilers ( Wood chips)
Capacity: 20 t/hr
Quanity: 2 off
Supply of APC Equip: 2 off BETH/ J&C Eng ESP’s
Erection Period: 3 Months
Guarantee Offered: Less than 50mg
Guarantee achieved: Less than 28mg